Show sample answer ▾▴
S: A platform project was 3 months behind and rated red. T: Recover without burning the team. A: I rebaselined the critical path, separated must-haves from nice-to-haves, renegotiated scope with the sponsor, and fixed the two dependencies actually blocking progress. R: Back to green in 8 weeks and delivered with the agreed reduced scope — not by demanding overtime.